Office Demising & Reconfiguration
Maynard, MA

HUB recently delivered a comprehensive office demising and reconfiguration project in Maynard, MA, following a tenant’s return of half their 60,000 SF floor. 

To support the transition, our team:

  • Constructed a large demising wall and fully separated mechanical, electrical, and plumbing systems — including installing submeters on all affected panels.
  • Matched the original build-out by sourcing and procuring carpet, lighting, ceiling tiles, doors, and hardware.
  • Completed a tailored reconfiguration featuring six private offices, a conference room, and a large storage area.
  • This project required both fire alarm and sprinkler adjustments to accommodate the new layout

Delivered on schedule, this project supported both the tenant’s downsizing needs and the building owner’s multi-tenant conversion goals.